Monday 29 December 2014

What's in Your Electricity Bill : Part 2 - Constraint Payments

Constraint Payments




Summary:


  • Constraint payments are paid when a plant is forced to run differently to schedule.
  • These payments have risen since 2009 from €101m to €175m in 2014.
  • Years with good wind output (high capacity factor) coincide with those years that had high constraint payments
  • This is because wind is intermittent and must be taken by the grid when available (priority dispatch). This results in plant running differently to schedule more often than in a system with little or no wind.
  • The cost of constraints in 2014 was roughly equal to the claimed fossil fuel savings by SEAI for 2012.
  • Older plant have been replaced by modern efficient plant which require longer start up times but should result in more efficient use of fuel. But because wind is running in and out of the grid intermittently, the new modern plant are running less efficiently than they are designed to. This adds to constraint costs.

Constraint payments are a form of compensation for a plant when it runs differently to its scheduled production. I will explain this in further detail below but first of all I need to clear up a few things. There are different forms of constraint payments. The type of constraint payments discussed in this article are paid to conventional plant, mostly gas.  According to the Department of Energy, curtailment payments in the region of € 7.5 million were paid to wind farms in 2013. Curtailment and constraints are, confusingly, when talking about wind energy, two separate things - one is when wind farms are shut down due to local constraint problems, the other is because of national constraints e.g. when the SNSP 50% limit is breached. As far as I can discern, wind farms do not receive the type of constraint payments discussed in this blogpost, as they are not given daily schedules - instead, they get priority dispatch, if and when the wind blows (between cut in and cut out speed). However, wind energy does contribute to higher constraint payments for conventional plant as we will see.

Let's look at the annual constraint payments for the last few years :



Annual Constraint Payments paid to conventional plant
(from SEMO http://www.sem-o.com/pages/MDB_ValueOfMarket.aspx)

2010 and 2012 were years with relatively poor capacity factors for wind. The other years had average to high capacity factors. In these years, we see higher levels of constraint payments as there was more unpredictable wind interrupting the scheduled generation for conventional plant . By 2014, the payments hit a peak of € 175 million due to two factors -  saturation of wind in the system and the new interconnector which provided power from cheaper sources such as coal.  We can see which direction the payments will go when we add more wind into the mix. To put the € 175 million into perspective, SEAI claimed that wind energy resulted in € 177 million in fossil fuel savings in 2012.

EirGrid and SONI foresaw these increased constraint costs in this report :

Wind is inherently a variable resource. The UUC market schedule [done after the event], with perfect foresight, can schedule the most economic generation to balance this variability as it knows exactly the level of wind output in every period. The TSO, on the other hand, since it is not always aware of the timing or extent of these variations, must balance them using a combination of part-loaded plant and more expensive fast-start plant. This less optimal schedule will cause an increase in constraint costs. 


They then go on to say :

The generation portfolio has changed in recent years due to closures of mid-merit plant such as Poolbeg Units 1 and 2 [blogger note - these are the two plant which used the famous, now redundant, chimney stacks in Ringsend, Dublin pictured above], and the long-term forced outages of a number of other mid-merit and flexible generation units, such as North Wall 4 and Turlough Hill. In addition, transmission constraints limit output from Aghada Unit 1 and the Aghada Gas Turbines at times, further limiting the available generation portfolio. This deficit of mid-merit units that can start with relatively short notice periods has resulted in a reduction in portfolio flexibility for reacting to unexpected changes in generation and demand. Previously, when these units were available, uncertainty over generation, wind and load could be managed within 1 to 2 hours using these flexible mid-merit generator units.
At present, any potential capacity shortages due to generation, wind and load uncertainty in the future require commitment decisions to be made a number of hours in advance due to the long notice periods required by the generator units available to meet these shortages. Operators are required to call units with long notice periods further from real time when there is greater uncertainty about forecast accuracy, thus increasing the likelihood that dispatch diverges more from the optimal solution.
These commitment decisions are made to mitigate against the risk of a capacity shortage
and to ensure that sufficient replacement reserve is maintained to deal with any further
changes to generator availability or forecast demand or wind. Availability of generation with shorter notice times would mean that such commitment decisions could be made nearer to real-time and with better information.
 
A provision of €3.8m has been included to account for divergence of dispatch from the
optimal solution due to generation portfolio changes. The return of Turlough Hill is expected to have a positive impact on the flexibility of the generation portfolio and the return of these generator units has been incorporated in the provision. So in otherwords, due to wind forecasting problems, there is further unpredictability in the system for conventional generators

So plant that could start up quickly (but were inefficient) were closed down and replaced with slower starting more efficient plant. This shouldn't be a problem as it should lead to more efficient use of fuel. But because it gets more difficult to forecast the wind accurately, particularly when at high penetration levels, you have to compensate these plants when they are forced off the grid by wind (which has priority dispatch) and forced to run differently to schedule.

Each plant is given a production schedule for the day. The older plants were given a schedule an hour or two before production because they could switch on quickly. But the slower modern plants have to be given their schedule up to 8 hours or more before production. The problem is that with high levels of variable wind in the system, this schedule is bound to change and plant must be compensated for these changes. Otherwise, they go out of business (which is not a good idea if you want to keep the lights on).

With wind energy now embedded in our electricity system and indeed in our energy policy, constraint payments are something we will all be paying for long into the future. It is another example of how wind adds complexity to the electricity system. A general rule in economics is that complexity costs money. You can imagine the level of office staff required to calculate the above for each and every plant in the country each day of the year. While nobody begrudges anybody a job, surely a limit needs to put on these added complexities if we want to remain competitive.


6 comments:

  1. Amazing the amounts of money paid to generators not to produce power.
    Currently the CER is changing the grid code to increase the RoCoF (Rate of Change of Frequency) to allow more wind or SNSP onto the grid from the current level of 50% to a theoretical 75%. This will have a number of adverse impacts including increasing the ramping of the conventional plant, leading to increased wear and tear.
    It will also increase the constraint payments paid to conventional plant.

    ReplyDelete
    Replies
    1. Just to clarify, the payments referred to in this blog would include power produced as well as power not produced. The key point is that when a generator acts differently to its schedule, it usually costs money. Otherwise, it doesnt become profitable for the plant and they go out of business.

      The plan to generate large amounts of electricity from variable wind with priority dispatch will result in significant levels of constraint to conventional plant. The constraint costs for 2014 were roughly equal to the alleged SEAI fossil fuel savings for 2012.

      Delete
  2. Another excellent blog. Increasing CER-permitted ROCOF is an inherently destabilising policy and mutually exclusive with high efficiency energy-balanced combined cycle generating plant. The faster that asynchronous generation can influence grid characteristics due to higher SNSP, the faster the reaction of spinning reserve has to ramp up or ramp down to counteract it.
    The wind farm operator should be responsible for maintaining supply at the connection point within specified stability criteria using technologies such as short-term blade-feathering and dynamic energy storage at the operator's expense. In other words, put the onus on the operator to make the wind farm present to the grid as a stable generator, rather than destabilising the grid with undisciplined supply.

    ReplyDelete
    Replies
    1. I agree that Wind farms should bear the additional costs incurred in the system with accommodating high levels of wind energy including changing the RoCoF, costs arising from inefficiencies of plant, dispatch balancing costs, additional transmission & distribution costs etc

      Delete
  3. Imagine you are running a supermarket in Mullingar. You employ 14 full time staff, 10 of which can cover the checkouts. You also employ 6 part timers for busy days and to replace absent staff . 2 of these can cover the checkouts, and you are competing with 2 other outlets locally. Margins are tight and staff are good.
    You receive a binding order from the Department of Labour that you must employ 6 people from the live register and pay them 25% more than permanent staff. These new ones will work only 25% of the hours of the permanent staff ,but can come and go as they wish, Monday morning, 12 mid night, 4 am whatever they want. They can leave work when they like, provided they work a quarter of the permanent staff's hours. You must give them work and if there is no place for 1,2,3,4,5 or 6 of them, you must pay them a slightly reduced rate and put them watching TV upstairs. You cannot schedule them for busy periods and you cannot give permanent staff a day off to be replaced by them. 1 or more may come in or may not. In fact all 6 might arrive in at 3 am when the shop is closed, so you have to employ a security man to mind the doors. and heat the TV room.You also have to employ an extra manager to manage the new staff arrangements. If 4 arrive in at 11am Wednesday, you must send 4 permanent staff upstairs to watch TV, but you cannot allow any to leave because the new ones often walk out after 20 minutes to make the hairdressers etc. Permanent staff complain that they are suffering fatigue from running up and down the stairs to replace new ones and find the new ones damages their routine. You receive word that the state is claiming the plan is reducing unemployment and the public seem to approve of it, but complain that it is cheaper to shop down the road or in the North where groceries are cheaper. You are finding that new staff are causing a lot of breakages and giving wrong change leading to refunds and customer dissatisfaction. All new ones work the till, but you feel only 3 are competent to do so. All most be treated equally, and you discover you must maintain 45% original staff or problems happen. You also discover that if you allow more than 50% of the staff at any one time to be new ones, all hell breaks loose because the new ones don't have the skills to run the shop by themselves. A fixed payment must be paid to all staff just to exist and the new ones get this too (capacity payments) That's one way to explain wind energy, which cannot be scheduled and must be paid for any way. This is a normal opening hours scenario.

    ReplyDelete
    Replies
    1. Now consider the above supermarket open 24 hours in Dublin. There are normally few customers between 1 am and 7am and you just keep 1 or 2 staff on. Now all 6 of the new ones occasionally arrive at various times during these hours. Some stay 2 hours and some 6 hours with no schedule. You still have to employ your original 2, there is not enough customers. You send one permanent staff and 5 news ones upstairs to watch TV. You ask the shop next door to employ some of the new ones, but they will only pay 20% of your wage bill. Sometimes the shop next door will only employ them if you pay them. A tax is put on you permanent staff to give a bonus to the new ones.

      Delete